Watch | India's first bullet train terminal at Sabarmati multimodal transport hub in Ahmedabad

India's first bullet train project is being built by the National High Speed Rail Corporation Limited (NHSRCL) between Mumbai-Ahmedabad. The first section under this project is expected to get ready by 2026.

Shashwat Bhandari Edited By: Shashwat Bhandari @ShashBhandari New Delhi Updated on: December 07, 2023 21:01 IST
Terminal for India's first bullet train at Sabarmati
Image Source : @ASHWINIVAISHNAW Terminal for India's first bullet train at Sabarmati multimodal transport hub in Ahmedabad.

Mumbai-Ahmedabad Bullet Train Corridor: Union Railways Minister Ashwini Vaishnaw has shared the glimpse of Terminal for India's first bullet train 'Sabarmati multimodal transport hub', in Ahmedabad, as the under-construction Mumbai-Ahmedabad high speed rail corridor advances.

Taking to Twitter, Ashwini Vaishnaw wrote, "Terminal for India's first bullet train! Sabarmati multimodal transport hub, Ahmedabad". Take a look. 

India's first bullet train project being built by NHSRCL

  • National High Speed Rail Corporation Limited (NHSRCL), is building the Mumbai-Ahmedabad bullet train corridor. So far, 100 kilometres of viaducts and 230 kilometres of pier work had been completed for the ambitious project.
  • The milestone of construction of 100 km of viaducts has been achieved through launching of 40-metre long 'full span box girders' and 'segmental girders'. The viaducts include bridges over six Gujarat rivers, namely Par and Auranga in Valsad district, as well as Purna, Mindhola, Ambika and Venganiya in Navsari district.
  • "The first girder of the project was launched on November 25, 2021, while the first kilometre of viaduct was ready in six months on June 30, 2022. It achieved construction of 50 kilometres of viaduct on April 22, 2023 and, thereafter, in six months 100 kilometres of viaduct were completed," the NHSRCL said.
  • "The Full Span Launching technique (FSLM), where 40-metre long box girders are launched by state-of-the-art equipment, is being used along with span-by-span launching of segments. FSLM is 10 times faster than the span-by-span method, which is normally used to build metro viaducts," it added.
  • According to the NHSRCL, apart from the viaduct work, 250 kilometres of pier work has also been completed for the project, while installation of noise barriers has begun along the constructed viaduct.
  • "Besides this, the laying of the first reinforced concrete (RC) track bed for the Mumbai Ahmedabad high speed rail corridor track system as used in the Japanese Shinkansen has also started in Surat," the NHSRCL said.

Bullet train project cost

The total cost of the Mumbai-Ahmedabad High Speed Rail Corridor project is pegged at Rs 1.08 lakh crore. As per the shareholding pattern, the Union government will pay Rs 10,000 crore to the NHSRCL, while Gujarat and Maharashtra are to pay Rs 5,000 crore each.

The rest of the cost is by way of a loan at 0.1 per cent interest from Japan. The foundation of the bullet train project was laid in Ahmedabad in September 2017.

The train is expected to cover a distance of more than 500 km in around two hours.

 

ALSO READ | India's first bullet train section to be ready by August 2026: Railways Minister Ashwini Vaishnaw

Advertisement

Read all the Breaking News Live on indiatvnews.com and Get Latest English News & Updates from India

Advertisement
Advertisement
Advertisement
Advertisement