CAG raps Def Min, Navy for mishandling submarine refit

New Delhi: The apex government auditor, the Comptroller and Auditor General of India (CAG) today came down hard on the Navy, Defence Ministry and a state-run shipyard for prolonged delay in the refit of submarine

India TV News Desk India TV News Desk Updated on: December 08, 2015 20:04 IST
cag raps def min navy for mishandling submarine refit
cag raps def min navy for mishandling submarine refit

New Delhi: The apex government auditor, the Comptroller and Auditor General of India (CAG) today came down hard on the Navy, Defence Ministry and a state-run shipyard for prolonged delay in the refit of submarine INS Sindhukirti, saying that the delay has deprived the force of one of their lethal platforms since June 2004. 

In its report submitted to Parliament, the CAG said that the medium refit of the EKM class submarine was due for commencement in 2001 but was carried out from January 2006. By that time, the material state of the vessel had witnessed "extensive deterioration". 

The report further noted that though the refit was scheduled to be completed by January 2009, deficiency in manpower deployed by the Hindustan Shipyard Limited, lack of protection to main line cables, delayed supply of yard materials and modernisation of equipment, the submarine was delivered by the shipyard to the Navy in June this year with Sea Acceptance Trial to follow. 

"As a result, the Navy is unable to operate one of their lethal platforms since June 2004," the report said. It also noted that the cost of the refit was revised from Rs 629.50 crore (June 2005) to Rs 999.52 crore (August 2013) with additional liabilities of Rs 92.17 crore still being claimed by the yard in September 2015. 

"This apart, improper financial management led to the diversion of funds to the tune of Rs 92 crore," the report said. 

In its recommendations, CAG said the planning and commencement of refit of submarines should be as per schedule to avoid excessive exploitation of vessels extension of refitting time. 

"The Ministry should ensure that efforts are augmented to improve the scale of utilisation of indigenous materials in line with its own directives. 

"The Navy should establish a dedicated Project Team, the expertise of which is available to each indigenous offloaded refit," the report said. The CAG also criticised the Coast Guard and the Defence Ministry for the delay in acquisition of inshore patrol vessels. 

(With PTI inputs)