  • fast against kudankulam n plant ends

    Fast against Kudankulam n-plant ends

    India | February 05, 2014 6:58 IST

    Chennai: An indefinite fast by the core committee members of the People's Movement Against Nuclear Energy (PMANE) and some villagers against the Kudankulam nuclear power project came to an end on its fifth day Tuesday.A

  • kudankulam n plant restarts power generation connected to

    Kudankulam N-plant restarts power generation, connected to grid

    India | October 26, 2013 7:11 IST

    Chennai: The first unit of the Kudankulam Nuclear Power Project (KNPP) that tripped Oct 22 was reconnected to the grid yesterday night, said a senior official."The unit was synchronised (connected to the grid) at 9.43

  • first unit of kudankulam n plant to join grid by month end

    First unit of Kudankulam N-plant to join grid by month-end

    India | August 16, 2013 17:23 IST

    Chennai: The first unit of Kudankulam Nuclear Power Plant is likely to be connected to the grid by this month end as Atomic Energy Regulatory Board has given its nod to increase power generation by

  • kudankulam n plant working smoothly experiments to end soon

    Kudankulam N-plant working smoothly, experiments to end soon

    India | July 24, 2013 7:40 IST

    Chennai, July 24: Everything is proceeding smoothly at the first unit of Kudankulam Nuclear Power Project (KNPP) and the low power experiments are expected to be completed by the end of this week, said officials

  • kudankulam n plant opponents seek emergency plan details

    Kudankulam n-plant opponents seek emergency plan details

    India | May 14, 2013 13:52 IST

    Chennai, May 14: Anti-nuclear activists have sought details of the emergency plan from the authorities to check their preparedness in evacuating people living within the 16-km radius of the Tamil Nadu's 1,000 MW Kudankulam Nuclear

  • four faulty valves replaced in kudankulam n plant says aerb

    Four faulty valves replaced in Kudankulam N-plant, says AERB

    India | April 20, 2013 8:40 IST

    Chennai, April 20:  India's atomic energy regulator Friday said four defective valves were replaced at the first unit of the Kudankulam Nuclear Power Project (KNPP) which is undergoing pre-commissioning tests."During testing of thousands of valves

  • ulterior motive behind stir against kudankulam n plant says

    'Ulterior Motive' Behind Stir Against Kudankulam N-Plant, Says Chidambaram

    India | March 26, 2012 12:20 IST

    Sivaganga (TN), Mar 26: Home Minister P Chidambaram has said there was “some ulterior motive” behind continuance of the protest against the nuclear power plant at Kudankulam despite assurance from the government that it is

  • jayalalithaa govt. gives go ahead to kudankulam n plant

    Jayalalithaa Govt. Gives Go Ahead To Kudankulam N-plant

    India | March 19, 2012 15:38 IST

    Chennai, Mar 19: Seeking to end the impasse over the Kudankulam nuclear plant issue, the Jayalalilthaa government in Tamil Nadu on Monday gave the go ahead to the controversial project and announced a Rs. 500

  • kalam says kudankulam n plant is fully safe

    Kalam Says, Kudankulam N-Plant Is Fully Safe

    India | November 06, 2011 19:07 IST

    Thirunelveli, TN, Nov 6 : Former President A.P.J. Abdul Kalam, who is on a mission to allay fears about the safety of the Kudankulam Nuclear Power Plant, on Sunday said it was ‘completely safe' as