DGH refuses to approve RIL's $3.5 bn plan for NEC-25

Mumbai, July 14: The Directorate General of Hydrocarbons (DGH) has refused to approve Reliance Industries' $3.5 billion plan for developing gas discoveries in block NEC-25, off the Odisha coast, as the company had not done

PTI PTI Updated on: July 14, 2013 12:48 IST
dgh refuses to approve ril s 3.5 bn plan for nec 25
dgh refuses to approve ril s 3.5 bn plan for nec 25

Mumbai, July 14: The Directorate General of Hydrocarbons (DGH) has refused to approve Reliance Industries' $3.5 billion plan for developing gas discoveries in block NEC-25, off the Odisha coast, as the company had not done the prescribed tests to confirm the finds. RIL had in March-end submitted a $3.5 billion Integrated Field Development Plan for producing 10 million standard cubic meters per day of gas from the discoveries D-32, D-40, D-9 and D-10 in the Block NEC-OSN-97/2 (NEC-25) by mid-2019.




DGH, the nodal technical arm of Oil Ministry, has however refused to bring the development plan to block oversight panel, called the Management Committee, for approval disputing commerciality of D-32 and D-40 in absence of Drill Stem Tests (DSTs) to confirm the finds. Sources with direct knowledge of the development said the issue has now been referred to the Oil Ministry as at least half a dozen discoveries in the now producing KG-D6 block of RIL and several of Oil and Natural Gas Corp (ONGC) had been declared commercial in past without DST being done.

RIL and its partner BP plc of UK, they said, have stated that DGH should have insisted on DST being done when discoveries were being appraised some years back and not now when development plan has come up for approval. They also feel DSTs are not just expensive proposition that will have bearing on government's profit take but also not conclusive tests to confirm production profile.

The sources said that on DGH insistence, RIL, operator of the block, has agreed to do DSTs but now the upstream nodal agency says the exploration phase of the block is over and so even those cannot be permitted. The Ministry, which has been pushing for speedy development of discoveries to raise domestic output so that imports can be cut, will now decide if DGH is right in insisting on DST now and not at the time of confirmation appraisals done some years back. DGH had recently rejected Declaration of Commerciality (DoC) of three discoveries in the flagging KG-D6 block on grounds of no separate DST being done.

The sources said DGH also refused to provide sanction for drilling of a well to carry out the requisite DST on finds in NEC-25 required to prove commerciality by claiming that the timeline for drilling such a well is over. It rejected an RIL attempt to begin pre-development activities on the ground that these discoveries cannot be treated as "commercial" in the absence of sustainable production testing data. According to RIL, D-32 and D-40 hold an inplace reserve of up to 663 billion cubic feet capable of producing 170 million standard cubic feet per day.